Data center revenue per MW: why published figures differ and how to compare them
Two figures for revenue per MW can be far apart without either being wrong. They may count different things, per different megawatts, over different periods.
Four figures, four bases
The examples are public and are here only to show how the basis changes a number. They are not a ranking of prices or deals, and we express no view on the companies or their securities. The companies named are public context, not our clients or partners. The amounts per MW per year are our calculation from the published figures, rounded.
| Basis | Per MW per year, our calculation |
|---|---|
| Colocation asking rent, per kW of a 250 to 500 kW requirement | about $2.4M |
| A long lease for AI capacity, per MW of IT capacity, average over the term | about $1.9M |
| The same lease, per MW of utility capacity | about $1.4M |
| A GPU cloud contract, per MW of critical IT load, average over the term, if the contract uses all 200 MW | about $9.7M |
Where each figure comes from
Colocation asking rent
CBRE reports that the average asking rate for a 250 to 500 kW requirement in primary wholesale colocation markets reached $196.25 per kW per month, in its report on North America for the second half of 2025 (CBRE).
Our calculation$196.25 × 12 months × 1,000 kW = about $2.4M per MW per year.
CaveatIt is an asking rate, not a signed one. The sentence we rely on does not say whether power is included or how the kW are defined. It applies to one size band and is not the revenue of a facility.
A long lease, per IT megawatt
On 17 December 2025 Hut 8 announced a lease for 245 MW of IT capacity, on a triple net basis, with a "total contract value of $7.0 billion over a 15-year base lease term, inclusive of a 3.0% annual base rent escalator" (announcement).
Our calculation$7.0 billion ÷ 15 years ÷ 245 MW = about $1.9M per IT MW per year, as an average over the base term.
CaveatWith an escalator, early years are below the average. If we assume rent rises 3.0% each year over 15 full years, with all capacity in service from the start, which a phased project may not match, the first year is about $1.5M.
The same lease, per utility megawatt
The same announcement gives an initial 330 MW of utility capacity for the campus, supporting that lease.
Our calculation$7.0 billion ÷ 15 years ÷ 330 MW = about $1.4M per MW per year.
CaveatThe total is the same; only the megawatt basis changes.
A GPU cloud contract
On 3 November 2025 IREN announced a GPU cloud services contract with Microsoft: "access to NVIDIA GB300 GPUs over a five-year term, with a total contract value of approximately $9.7 billion, including a 20% prepayment". The announcement says the GPUs are expected to be deployed in phases through 2026, "in conjunction with the delivery of new liquid-cooled data centers that will collectively support 200MW of critical IT load" (filing).
Our calculationIf we assume the contract uses the full 200 MW: $9.7 billion ÷ 5 years ÷ 200 MW = about $9.7M per MW of critical IT load per year, as an average over the term.
CaveatThis sells computing on the operator's GPUs, not only space and power. The prepayment is part of the total, not an addition to it.
Seven questions to compare any two figures
1What is sold?
Space and power, computing on GPUs, or a service built on it. These layers sit inside one another: a GPU operator pays for the facility out of its revenue, so do not add the layers together. A revenue level needed to reach a target return is a model requirement, not a market figure.
2Per what period?
To turn a price per kW per month into an amount per MW per year, multiply by 12,000.
3An average, or a given year?
Total contract value divided by years is an average. Escalators, phased delivery and free periods change single years. Leave renewal options out unless you say you counted them.
4Which megawatt?
IT or critical IT load, utility or gross capacity, contracted or active power, or just "MW". If the basis is not named, say so instead of guessing. PUE, as The Green Grid describes it, "illustrates the total energy used by a data center divided by the energy used by ICT equipment in that data center". Uptime Institute reports an industry-wide annual average of 1.52 from its 2026 survey, and 1.36 when larger facilities get proportional weight. PUE is a ratio of energy, so do not use an average PUE to convert one announced capacity into another. Where a source gives both capacities, use that pair and say what each one is.
5What does the payment cover?
Power, taxes, insurance, maintenance, software and support, and any prepayment. A triple net lease and an all-in price are not the same product.
6How firm is the number?
An asking price, a signed price, a total contract value, a run-rate estimate and recognized revenue are five different things.
7For GPU revenue, which assumptions?
GPU generation, GPUs per IT MW, price per GPU-hour, share of hours paid and contract term. For one year: revenue per IT MW = GPUs per IT MW × 8,760 hours × price per GPU-hour × share of hours paid.
Revenue per MW is not return
In these examples the amount per MW is highest for the GPU contract, because it sells computing on the operator's GPUs. That needs equipment of its own: in the same announcement, the operator says it agreed to buy the GPUs and ancillary equipment for approximately $5.8 billion. To judge return you also need capital cost, operating cost, financing, the useful life of the hardware and what happens when the contract ends. None of the figures on this page is investment advice.
How we help
We model service economics in the financial model: the GPU-hour price and utilization at which a project pays back. For an investor or lender, we check the developer's capex, schedule, power, hardware and financial model against our reference model.
Questions we hear
What is the revenue per MW of an AI data center?
There is no single figure. State what is sold, which megawatt is counted, the period and how firm the number is, and compare only figures that match on all four.
Which basis should a project use?
Show the basis next to every figure, and keep one basis across a document. If you show more than one, label each.
Are these your estimates?
The source figures are published by the organizations linked here. The amounts per MW per year are our arithmetic on those figures, and the first-year amount rests on the assumption stated with it. None of them is a view on any project.
Sources
- CBRE: North America Data Center Trends H2 2025, 25 February 2026.
- Hut 8: announcement of the River Bend lease, 17 December 2025.
- IREN: announcement of the contract with Microsoft, filed with the SEC, 3 November 2025.
- The Green Grid: PUE.
- Uptime Institute: The growing PUE advantage of larger data centers, 6 August 2026.
Pages checked on 25 November 2026. Publishers update their pages; check the source before you rely on a figure.